Showing posts with label Community/Senior Center. Show all posts
Showing posts with label Community/Senior Center. Show all posts

Wednesday, June 11, 2008

Community/Senior Center

Laguna BeachInstallation of the mechanical, plumbing, HVAC, and electrical systems are actively underway. As these systems are completed, exterior and interior walls are completed. Site improvements on Loma Terrace and Mermaid will commence soon.

Monday, May 19, 2008

Community/Senior Center

Laguna Beach

Friday, May 09, 2008

Community/Senior Center -- Two Roof Sections Remain

Laguna BeachLaguna Beach

Friday, May 02, 2008

Community/Senior Center - Soon The Roof Will Be Complete

Laguna Beach

Tuesday, April 29, 2008

Community/Senior Center - Roof Trusses Installed

Laguna Beach

Friday, April 25, 2008

Community/Senior Center - Soon The Roof

Laguna BeachLaguna BeachThe roof trusses will arrive Monday.

Thursday, April 10, 2008

Senior/Community Center The Walls Are Raising

Laguna BeachLaguna BeachLaguna BeachLaguna Beach

Thursday, April 03, 2008

Community/Senior Center - Soon The Roof

Laguna Beach

Monday, March 10, 2008

Community/Senior Center

Laguna BeachLaguna BeachThis photo shows where the sculpture was going to be placed at the Community / Senior Center. What we have now is a big notch cut out of the building. So what to do with it? That's the question. We suggest that a very large tile mosaic be put up along with a fountain. Just so long as it's not another whale!

Friday, March 07, 2008

Community/Senior Center

Laguna Beach
The steel is being installed at a quick pace. Soon the roof will be going on. We look forward to this.

Monday, February 25, 2008

Steel For The Senior/Community Center

Laguna Beach

Friday, February 15, 2008

Senior/Community Center Moving Ahead

Laguna BeachLaguna BeachThere are rumors that they're ahead of schedule.

Friday, February 01, 2008

Senior/Community Center The Walls Are Raising

Laguna BeachThe walls of the building are raising at a fast clip. Could we be seeing the roof going in place next month? We will keep you posted.

Wednesday, January 30, 2008

Senior/Community Center A Work In Progress

Laguna BeachLaguna BeachLaguna Beach

Thursday, January 24, 2008

Senior/Community Center Final Pour?

Laguna BeachThe concrete pour for the main floor is being completed today. That may be the last major concrete pour for the center. There may be another for the roof. Concrete roof? Now that we gotta see.

Thursday, January 17, 2008

Senior/Community Center Concrete Pour Next Wednesday

Laguna BeachThe schedule calls for another concrete pour next Wednesday. Be prepared and avoid 3rd St that day.

Wednesday, January 16, 2008

Community/Senior Center Moving Right Along

Laguna BeachAnother concrete pour should be real soon.

Friday, January 11, 2008

Community/Senior Center

Laguna BeachLaguna BeachReinforceing bars for the remainder of the first floor arrived today.

Clinic Gets Temporary Parking

Laguna BeachDuring month of January, the contractor for the community center needs to tie into the existing City storm drain which runs along the Community Clinic property. Working with the Clinic, the contractor will need to use their driveway and several of their on-site parking spaces. As replacement spaces, the city will reserve nine on-street parking meters for the Community Clinic.

Friday, December 21, 2007

The Pour Continues

Will probably continue until 4pm or 5pm.